West Lake STEM Jr. High Construction Tour – April 2024
Status of Projects April 2024 – West Lake STEM
Updates:
- Permanent power to the site is connected. Exterior glazing is 95% complete. The two rooftop air handling units serving the Gymnasium have arrived
- In the Athletic Wing and the Kitchen, the electrical rough-in is 75% complete. The floor and wall tile are also 75% complete.
- The stage rigging in Performing Arts is being installed.
- In the CTE Wing, the mechanical, electrical, plumbing installation and the interior paint work is moving forward.
- The Academic and Administration Wings are progressing with cabinetry installation. The diffusers and grills are 85% complete.
Status of Projects April 2024 – Skyline High School
Updates:
Academics
● Ceiling cloud being installed in Cafeteria Area
● Stone cladding complete at Main Entrance
● Lighting installed in Cafeteria
● Glass installed in majority of classroom groups
● Carpet complete on Level 2
● LVT starting in corridors
● Tile started in group restrooms on north end of building on all floors
● Ceiling grid started on all floors
● Cabinetry started on Level 1
● Doors being installed throughout entire building
● Countertops installed in science labs on Level 3
● Restroom accessories being installed
Recent Pictures:
Level 1 restroom
Performing Arts
the Cafeteria
Status of Projects April 2024 – Cyprus High School
Updates:
Building Exterior:
● Glass installation at the Auditorium
● Glass installation at Academics
Athletics/Pool:
● Pool excavation/footings
● Tile in Pool locker rooms
● Ceiling tile in Athletics Vestibule
● Tectum panels in Weight Room
Administration/Commons:
● Slab on grade in Cafeteria Area of Commons
● Level 1 framing and HVAC in Administration
● Level 2 and 3 framing
Academics/Social Studies:
● Framing Level 2
● Framing and electrical Level 3
Performing Arts:
● Drywall on the Proscenium
● Paint and framing in Scenery Shop
Recent Photos:
Status of Projects Update: April 2024
Watch the presentation in the video below for updates about Granite School District construction projects (1:05:50 – 1:19:21). This presentation was given in the April 2024 Board of Education Meeting. Click here for a copy of the slides.
Skyline Construction Update Video – March 2024
Status of Projects March 2024 – Skyline High School
Updates:
Academics
●High ceiling in Cafeteria painted
●Exterior glass complete at Main Entrance
●Metal wood look soffits near completion in Cafeteria
●Storefront glass frames installed at Media Center
●Interior glass in classroom groups started
●Carpet and electrical trim started in Level 2 general classrooms
●Cabinet installation ongoing in Level 3 Science classrooms
●Painting on Level 2 near completion
●Main Corridor tile complete on Levels 2 and 3
●Tile at the Smoothie Bar complete
●Plumbing fixtures set in Administration Suite bathrooms
Recent Pictures:
Cafeteria/Commons
Status of Projects March 2024 – West Lake STEM
Updates:
- The three Academic wings are having countertops installed on cabinets, sinks installed in the restrooms, and wiring and sensors placed in the ceilings.
- The Administration wing has cabinets ready to be installed.
- The Serving area has decorative wall tile being installed.
- HVAC ducts are 90% complete.
Status of Projects March 2024 – Cyprus High School
Updates:
Site Work/Mechanical Yard:
●Footings/foundation at the Softball, Baseball Field
●Setting the generators into place
Athletics/Pool:
●Track Handrail Shoe
●Locker being placed in the PE Locker Rooms
●Pool painting
●Window caulking
Administration/Commons:
●Level 3 framing
●Level 1 slab on grade pour
●Prepping slab on grade in the Public Square/Dining
Academics/Social Studies:
●Framing of classrooms and display cases
●Drywall around the skylights
●Frames and glazing on the stair tower
●Finish paint on Levels 2 and 3
Performing Arts:
●Curtain wall and glazing around the Lobby
Recent Photos:
Academics Building
the Academics Building
- 1
- 2
- 3
- …
- 16
- Next Page »